ENGINEERING CASE STUDY

Antriebssystem für die Wartung von Windkraftanlagen

Projektspezifische Konstruktion, Fertigung, Prüfung und Lieferung eines Antriebssystems für die Wartung von Windkraftanlagen.

why_fictiv_front_3.webp
Project Background

Project Background

The customer required a reliable replacement or new-build hydraulic solution while maintaining the existing equipment interfaces and operating sequence.

Key Challenges

Critical challenges included limited installation space, demanding duty cycles, environmental exposure and documentation requirements.
why_fictiv_front_4.webp
Yongjian's Solution

Yongjian's Solution

The engineering team reviewed operating data, prepared interface drawings and configured materials, seals, controls and test procedures for the application.

Technical Configuration

The final configuration combined application-specific hydraulic components, structural interfaces and monitoring requirements.

Manufacturing & Testing

Manufacturing followed controlled machining, welding, assembly, pressure testing and documented inspection stages.

Delivery / Commissioning

The equipment was preserved, packed and delivered with drawings, records and installation guidance.

Project Results

The delivered system met the agreed functional and interface requirements and provided a documented basis for future maintenance.

Technical Configuration

Project Year2024
LocationNorthern Europe
ScopeEngineering, manufacturing, testing and delivery
why_fictiv_front_3.webp
why_fictiv_front_4.webp

Build a Custom Hydraulic System

From hydraulic schematics and component selection to fabrication, load testing, and commissioning support, Yongjian provides a coordinated engineering process.